China Naming Network - Eight-character fortune telling - What are the basic steps of all-inclusive decoration? Has the all-inclusive renovation been completed?

What are the basic steps of all-inclusive decoration? Has the all-inclusive renovation been completed?

What are the basic steps of all-inclusive decoration? All-inclusive refers to the contracting of materials. All materials are purchased by the construction party, and the owner, that is, Party A, only needs to pay.

All-inclusive decoration steps are as follows:

Decoration generally begins with disclosure.

Commencement disclosure: The designer (if any), foreman, supervisor and owner need to specify the process, acceptance criteria, additions and deletions on site. About half a day. ? Note: If demolition is required, check the items that need to be kept on site, such as balcony doors and windows, air conditioners, water heaters, furniture, etc. The owner needs to inform the foreman how to deal with it.

Demolition: about 3~5 days.

Water and electricity disclosure: more important. If there is a water purifier coming with the garbage disposal unit, if there is floor heating, fresh air and central air conditioning, you need to negotiate the order with the foreman. About half a day. ? Note: It takes 3 days for floor heating, 2 days for fresh air and 3 days for central air conditioning. Heating reform, gas meter shift, brick selection, metering cabinet, metering window, etc. It can be done before or before publication. Foundation construction generally starts with hydropower.

Hydropower renovation: Before renovation, water will enter electrical materials. Pay attention to water and electricity slotting and air conditioning punching, and arrange construction if there is a wall-mounted toilet. Windows and measuring entrance doors can be installed during hydropower construction. About five to seven days.

Water and electricity acceptance: about half a day. ? Note: After acceptance, according to the switch panel configuration provided by the plumber, prepare to buy switch panel, angle valve, floor drain, ventilator, etc.

Indoor structural transformation: new walls or partitions, bars and the like can be carried out at the same time as water and electricity. About 3~5 days.

Grooving and cement leveling of kitchen and bathroom walls: there is no problem in water and electricity acceptance, and the new walls can be grooved and leveled, and the balconies are insulated together. About 2 days. ? Note: remember to say hello to the neighbors downstairs in the meantime. You will have a waterproof and closed water test, leave your contact information, and maybe go downstairs to check for leaks.

Waterproof and closed water test of kitchen and balcony: During this period, the floor can be selected, and the optional floor thickness can be determined according to the ground. Set the threshold, and prepare the flue check valve, external corner strip and jointing agent for tiling. About 3~5 days.

Tiling kitchen and balcony: after tiling, notify cabinets and manufacturers to prepare the copy quantity, and notify door factories (wooden doors and metal doors) to measure on site. After installing the entrance doors, tile or ground cement shall be used for leveling. About 3-4 days.

Brick leveling of cement floor: pay attention to sprinkling water on the floor after drilling, and do both tile and cement floor. During this period, water heater, flue check valve, smoke pipe and gas pipe were installed, and the kitchen and bathroom ceiling manufacturer was informed to make on-site measurement. About 3~5 days.

Carpenters make ceilings, background walls, etc. /5~7 days: carpenters make decorative shapes such as ceilings, background walls, passages, partitions, etc. Remember to inform the door manufacturer to measure again after finishing it, and then scrape plaster or putty after installing the windowsill stone. About five to seven days.

Plastering and leveling of wall surface and top surface: paste plastering lines after leveling. During this period, you can choose sanitary ware, electrical appliances and furniture, and make an appointment with furniture manufacturers for home measurement. About 2-3 days. ? Note: buy paint before scraping putty at the latest. Some workers are used to painting different paints with different tools. Remember to say hello.

Oil workers scrape putty for 2~3 times: about 3~5 days. Note: be careful not to scrape putty in rainy days, and scrape putty after it is completely dry every time.

Putty polishing: 1~2 days or so.

Brush one bottom and two sides or paste wallpaper: during this period, kitchen and bathroom and balcony ceiling can be carried out, and switch panels and lamps can be installed. About 2-3 days. ? Note: Don't listen to the foreman's bluff. Don't brush the primer after polishing. Priming is effective. Brush primer to prevent the bottom layer from returning to alkali, prevent corrosion, increase paint adhesion and reduce the amount of topcoat. After loading the main material?

Cabinet installation: about 1 day.

Door installation: installed behind cabinets and large pieces of furniture to avoid damaging the door when the big board enters and exits. About 1 day.

Floor installation: first guard the door and floor, not fixed. About 1 day.

Bathroom installation: about half a day.

Repair the wall: the extra tiles can be returned, and the main materials such as wooden doors can be repaired. About clearing the land and cleaning. About 1 day.

Put essence in furniture: generally put essence for more than one month, during which soft clothes can be added. About 35 to 60 days.

Move into (a new house)

It takes a long time from decoration to occupancy, so you need to know it when you have time.