China Naming Network - Ziwei knowledge - 1 10kv sample of supervision log of tower foundation pouring construction.

1 10kv sample of supervision log of tower foundation pouring construction.

You can take a look at the following example: July 20, 2004 Weather: Sunny Temperature: Wind:

1, test

××× Bridge: Piles 6# of Pier 8, 6# of Pier 4, 3# of Pier 6 and 2# of Platform 0 are being drilled (impacted); 2# pier foundation pit is being excavated;

Gravel pile: except for 7#, 10 ~ 12 # and 1 # ~ 2 # which have not entered the pebble and have resumed work, the other pile drivers are under construction;

DK×××+ 109 culvert side sample masonry construction, and a set of mortar specimens were extracted;

There was no jet grouting pile construction in the morning (DK×××+383 culvert foundation treatment).

The action at the gravel pile construction site told XXX, the site supervision engineer of gravel pile, to take the time to sort out the data and related construction charts and make a summary.

2. Re-inspection

14: 30 quality inspection engineer ×× year × month × day × month × day × month × day × month × day × month × month × day × month × month × day × month × month × day × month × month × day × month × month × month × month × month × day × month × month × month × month × month × month × month × month × month × month × month × month

Quality inspection of reinforcing cage, length13.60+1.68, 12.80+ 12.46m, diameter 1. 13m, main reinforcement.

17: 00: Self-inspection of steel bar butt welding and stirrup binding threshold.

The depth of the cone tip is 27.46m.

The total length of downcomer is 27. Meter (short for meter))

Specific self-inspection, its ratio is 150: 289: 454: 54: 0.375, dry bamboo cement. Position: Bai

Before 19: 06, pour concrete (5 buckets) for back sealing, with the borehole depth of 25.70, the buried depth of conduit1.30m, and the side station: ×××××.

3. Achievements requiring communication and coordination

There are achievements between drawings, no XX and drawing number XX; Xx major needs to tell him to enter the site early and remind him to pay attention to safety and finished product maintenance; Data consumption test needs to enter the market, do a good job in re-examination and three certificates reflection career.

3. Report

17:15 ~17: 55 report the underwater C20 concrete mix ratio and some achievements (weak technical strength, silt content in pebbles) to the director's representative. XXX said: According to the mix proportion provided by Nanchang, the construction can be stopped, and samples will be sent to four projects for experiments in the future.

4. Telephone instruction: 2 1: 20, I will receive a phone call from the representative of Director XX, telling my subordinates to reflect on indoor and outdoor work at 9: 30 tomorrow morning.