Quality and safety special labor competition implementation plan Quality labor competition implementation plan
Waterway Regulation Project of Dongtai Section of Shen Lian Line
Implementation plan of quality and safety special labor competition
Jiangsu Taikang engineering supervisory co., ltd
LSX-DT-QLJL standard supervision team
July 28, 1965 438+02
In order to consolidate the achievements of "Labor Competition in the Second Quarter of Dagan" and "Safe Production Month", further implement the spirit of the project management office document (Yanlianhang Interstitial Office [2065 438+02] 12) of the Dongtai Section of Yancheng Shen Lian Line, ensure the project quality, solidly promote the construction of "safe construction site", further stimulate and mobilize the enthusiasm and creativity of the majority of project builders, and enhance the sense of ownership. In order to successfully carry out labor competition activities, the Bridge Bid Supervision Team of the waterway regulation project in Dongtai section of Shen Lian Line has specially formulated this scheme.
First, the guiding ideology:
Adhere to the guiding ideology of "safety first, quality first" and fully mobilize the enthusiasm, initiative and creativity of all employees to participate in the construction. Taking quality as the core, ensuring construction safety as the basis, strengthening management as the means, scientific and technological innovation as the driving force, and promoting the safety, high quality, environmental protection and harmony of engineering construction as the goal. Adhere to meticulous construction and strict management, improve the quality of the project in an all-round way, and ensure the qualified rate of the first inspection of the project 100%.
Second, the quality and safety labor competition leading group:
In order to make the quality and safety labor competition activities go smoothly and achieve practical results, the following leading groups are established:
Team leader: Han Yu (chief supervision engineer: responsible for the overall work of the supervision department, and fully responsible for project quality, safe production, construction progress and clean government construction)
Member: Huang Xinghua (fully responsible for project quality, construction progress and clean government construction)
Zhang Honghua (overall responsible for project safety production)
Wu Zhanlong and Jiang Wei (fully responsible for the first bid section of the bridge)
Xu Xueyou and Yan (fully responsible for the second bid section of this bridge)
Liu (overall responsible for bridge standard test)
Yan (fully responsible for bridge standard survey)
Wang Qinggui (overall responsible for bridge head wiring project)
Three. Competition scope, theme, objectives and contents:
Competition scope: QLSG 1, QLSG2, QLJL of waterway regulation works in Dongtai section of Shen Lian Line.
Competition theme: Carry out quality and safety special labor competition activities.
Competition goal: strictly implement the construction of each construction process and link, create a "demonstration site", implement safety responsibilities, put an end to hidden dangers of accidents and strive for excellent projects.
Competition content: Take the special labor competition of quality and safety as the starting point, comprehensively improve the project quality, ensure the first-time acceptance rate of the project 100%, ensure the comprehensive realization of the governance objectives in the Implementation Plan for Governance Activities of Common Concrete Quality Diseases of Highway and Waterway Projects in Jiangsu Province, firmly establish the awareness of "quality first" among all construction workers, strictly implement the construction procedures and links, and strive for excellent projects and "Yangtze Cup". Focusing on the goal of creating a "demonstration site", we will implement safety responsibilities, improve rules and regulations, find out potential safety hazards, and put an end to violations.
Work behavior, put an end to accidents, and achieve a safe summer.
Four. Competition-related requirements and rules:
(1) Relevant requirements and regulations of the supervision group:
In order to speed up the construction of waterway regulation project in Dongtai section of Shen Lian Line, we will strive to build the bridge project into a demonstration project with excellent quality, short construction period, less investment, beautiful environment and good benefits. Our supervision team has been stationed at the site according to the supervision contract personnel, and the invested supervision personnel strictly implement the national laws and regulations and the rules and regulations of the unit, have good professional ethics, unite and cooperate, have strong safety awareness, and strive to ensure the high quality, high standards and high requirements of the project. Implement management work from the following aspects.
1, project quality objectives
Strictly implement the requirements of design and specifications, and require the construction bid section to fully implement the principles, policies and technical standards of quality assurance, so as to standardize the construction site, site appearance and quality management. The qualified rate of unit project, divisional project and sectional project is 100%. Implement standardized construction to prevent common quality defects and major quality accidents. The quality assurance system operates normally, strictly implements relevant national codes and regulations, innovates technology, saves energy and reduces consumption, and strives for high-quality projects. Quality management responsibility system implementation rate 100%, concealed engineering site inspection rate 100%, process inspection rate 100%, qualified rate of raw materials such as steel bars, cement, sand and gravel 100%, qualified rate of partial projects 100%. There were no major engineering quality accidents.
Strict implementation of the Ministry of communications "highway engineering quality inspection and evaluation standards" and other specifications and the requirements of the project office.
Quality management measures, to ensure the effective operation of the quality assurance system, quality inspection data are true, timely and accurate, and synchronized with the project progress. Its activities and priorities are as follows:
(1) In order to ensure the effective operation of the quality assurance system and implement the responsibility of production quality management, the general manager Han Yu is responsible, and each section chief and professional engineer cooperate to effectively implement the responsibility of production quality management and control common quality defects.
Clarify the quality management rules, regulations and responsibilities of each section chief and professional engineer, and earnestly implement the standardized construction, quality education and training system, three-level technical disclosure system, three-level self-inspection system, test and detection standard, frequency and system, quality control measures for important and difficult points, preventive measures for common quality defects and quality accident reporting system.
(2) Strictly implement the examination and approval system.
The construction organization design and overall progress plan submitted by the contractor shall first be reviewed by various professional supervision engineers and put forward review opinions, and then approved by the chief supervision engineer within the time limit stipulated in the contract. The key points are:
1) Whether the examination and approval procedures for construction organization design are complete and effective.
2) Whether the construction quality, safety, environmental protection, progress and cost objectives are consistent with the contract.
3) Whether the quality, safety and environmental protection guarantee system is sound and effective. In the quality assurance system audit, the focus is on whether the construction self-inspection system is perfect, including whether the self-inspection personnel have technology and experience, whether the self-inspection person in charge is full-time, and whether the responsibilities and requirements are clear.
4) Safety technical measures, temporary electricity utilization scheme on the construction site and engineering emergency rescue.
Whether the insurance scheme meets the requirements.
5) Whether the overall construction deployment, construction scheme and emergency plan for safety and environmental protection are reasonable and feasible. For sub-divisional, sub-divisional and dangerous sub-divisional projects with complex technology or adopting new technologies and new processes or special seasons, the contractor is required to prepare special construction plans, which will be implemented after being reviewed by relevant professional supervision engineers and approved by the chief supervision engineer.
(3) Strictly implement the on-site construction procedure inspection system.
The steering group will seize the key point of "inspection". According to the requirements of technical specifications, the inspection points should be encrypted as much as possible, and the inspection depth should be strengthened to achieve "whole process, all directions and all links", so as to find and stop any unfavorable factors or signs of quality accidents that may affect the final quality of the project at the scene as soon as possible, deal with the existing technical or quality defects in time and ask the contractor to take measures to correct them.
Engineering quality supervision should carry out the whole process, all-round and all-weather quality management of the project, emphasize the supervision in advance and active supervision, strictly control the start-up and the construction process, so as to find problems as early as possible, nip in the bud and minimize and prevent undue accidents and losses. Implement the quality veto. According to the requirements of the owner, this project adopts the first article approval system. Each division (sub-project) is ready for the first inspection. The next working procedure can only be carried out after the supervision and inspection are qualified, and the unqualified working procedure should be repaired or reworked by the contractor. We should strengthen process control. The last working procedure shall not be carried out without inspection and approval, which is the magic weapon to eliminate quality hidden dangers and the key to ensure engineering quality.
(4) Strengthen the prevention of common quality defects and the control of key and difficult points, and attach great importance to the governance of common quality defects.
The supervision team shall conduct quality inspection on the construction bid section once a week, and the construction bid section shall conduct quality inspection on each ZuoYeDui once a day. Quality inspectors at all levels should do a good job of daily on-site inspection and make corresponding records. It is required that the construction bid section should combine the common quality faults and preventive measures in the quality assurance system, control the key points and difficulties, clarify the responsible person and team for the identified quality hidden dangers, formulate rectification measures and determine the rectification time.
(5) Organize learning and implement standardization construction.
From time to time, the supervision team will organize the main leaders of the construction unit to go to the brother units for on-site observation, study, training and other activities, exchange the experience and achievements of standardized construction work, and improve the standardized construction management in combination with standardized management system, process control, staffing and on-site management.
2, the project progress goal
This supervision contract section is the QLJL bid for the waterway regulation project of Dongtai section of Shen Lian Line, with 7 bridges, namely Zhendong Bridge, Yongxin Bridge, Anyu Bridge, Xinzao Bridge, Tongyu River Bridge, Wangang Bridge and Liang Yi Bridge. The supervision team will take effective measures to ensure the realization of the time limit for this project.
In order to ensure that the annual progress plan is realized by the end of 20 12, the leader of the supervision team organized an internal mobilization meeting for supervision, deployed the work of various departments and made corresponding plans.
Measures:
(1) Urge the construction unit to submit the progress plan.
① Compare the actual progress with the planned progress every half month (3rd of each month,18th), analyze the investment plan, find out the reasons for deviation in time, and make adjustments in time.
(2) Require the construction unit to strictly implement the construction plan approved by the supervision team during the construction process. If the construction unit fails to carry out the construction according to the approved construction schedule, the supervision team will order it to correct it immediately and require the construction to be carried out according to the approved plan.
(2) Progress inspection records
(1) requires the construction unit to record the actual progress according to the unit, division and subdivisional work, and conduct inspection, as the basis for mastering the project progress and decision-making, and count the actual and accumulated quantities of work every half month; The number of manpower and machinery actually involved in the construction every day; The number of manpower and machinery that stopped construction on that day and the reasons; On the same day, the supervisors and technicians of the construction unit arrived at the site; Special events or reasons that affect the progress of the project that day; The weather conditions of the day, etc.
(2) On-site supervisors must make a statistical summary of the progress of the project every day and communicate the progress with professional supervision engineers every day.
(3) The professional supervision engineer should pay attention to the progress of the project every day, and handle the abnormal situation in time (those that cannot be handled should be reported to the director for handling).
(3) Do a good job of internal assessment of the supervision team.
(1) requires supervisors to enhance their sense of responsibility and pay special attention to the progress of the project while ensuring the safety and quality of the project.
(2) Conduct professional and technical training for supervisors on a regular basis. Reward those who play an important role in promoting supervision and have outstanding performance. During the assessment period, those who have a bad or adverse impact on the work of the supervision team will be punished.
3, engineering construction safety objectives
Put an end to major engineering casualties, strictly implement the responsibility system for production safety, and conscientiously implement various safety production operating procedures and safety inspection systems, hidden dangers rectification systems, accident reporting and accident investigation systems.
(1) According to the requirements of carefully combining the standardized management regulations of the project office, the safety management of bid section 20 12 was planned, and the publicity and implementation were well done.
(2) Do a good job in standardized management of 20 12 safe and civilized construction, promote the solid and effective development of safety management, ensure the stable improvement of safety production situation, and carefully formulate and implement safety technical measures plan.
(3) Strengthen monitoring, save for a rainy day, carefully organize hazard identification and filing, earnestly strengthen the guidance on the supervision and management of major hazard sources in this bid section, ensure that the work objectives and work plans formulated are implemented to people, and pay special attention to safety management throughout. Conscientiously implement the policy of "safety first, prevention first, comprehensive management" and the responsibility system for production safety, strengthen production safety, labor protection and safety training, increase investment in safety and implement safety measures.
Ensure the overall construction safety of the project. Realization: no casualties, no major accidents and zero accident rate 100%.
4, project supervision and clean government construction goals
Further strengthen the responsibility system for building a clean and honest government, innovate the risk prevention and control mechanism, pay close attention to the source of corruption, ensure that there are no major cases, and create a clean and sunny demonstration site. Safe operation of construction funds, sunshine control of material procurement, comprehensive and efficient standardization. Understand the first-line situation, solve the first-line problems, and ensure that major petitions and mass incidents do not occur. Actively carry out study and training, build learning organizations and individuals, and comprehensively improve the performance of all contractors. Fully implement the responsibility system for building a clean and honest party style. Strictly abide by all laws and regulations. Strengthen source supervision, take the initiative to accept supervision, realize comprehensive management, and build a clean and sunny project. The signing rate of double contracts for "engineering construction" and "building a clean government" was 100%, and no cases of violation of law and discipline occurred. Investigation rate of disciplinary cases reported by the masses 100%.
(1) Earnestly implement the work requirements of the provincial government on the construction of a clean and honest government, with the same deployment, implementation, inspection, assessment, rewards and punishments, so as to achieve a clear division of tasks, responsibilities to people, working institutions, work arrangements, work measures, inspection and assessment methods, and accountability system.
(two) conscientiously implement the responsibility system for the construction of a clean and honest government, supervise, inspect and assess the construction of a clean and honest government within the scope of responsibility, and put forward suggestions for commendation, reward and accountability.
(3) adhere to the symptoms and root causes, comprehensive management, in strict accordance with regulations and procedures, knot.
According to the working characteristics of this project, aiming at the weak links that are easy to induce corruption in management, improve the management mechanism and supervision and restraint mechanism in time to prevent and control corruption from the source.
5, increase the publicity of quality and safety special labor competition.
Widely publicized and launched at different levels. Various forms and channels (posters, slogans, internet, meetings) should be used for in-depth publicity and mobilization work in each construction bid section, so that the general contractors can fully understand the significance, contents, practices and requirements of the competition and the tasks and objectives of the competition activities in this project, so that everyone can know and all employees can participate. During the competition, propaganda slogans will be laid on the project construction site and each bid section, and the progress of labor competition will be tracked throughout. Vigorously publicize the bid sections, construction classes and individuals with obvious work results and outstanding work performance in project construction and competition activities, and strive to create a good atmosphere for project promotion.
(2) Relevant requirements and detailed rules for construction bidding
Resolutely implement the party's basic line, principles and policies, adhere to the construction of two civilizations together, abide by national laws and regulations, unite as one, rely on the broad masses of workers wholeheartedly, and make remarkable achievements in engineering construction. Implement quality, safety, clean government and democratic management.
1, project quality:
(1) Adhere to quality first, actively implement the quality management responsibility system, and have a sound quality management system and quality excellence plan.
(2) Strictly implement construction specifications and establish rules and regulations and project management system.
(3) The qualified rate of subdivisional work is higher than 95%, ensuring that the qualified rate of unit project is 100%.
No permanent defects and engineering quality accidents.
2. Progress:
(1) scientifically prepare the project schedule according to the contract time limit and the overall construction requirements of the project. (2) Strictly implement the approved project construction progress plan, report the project progress report in time and feed back the project information.
(3) On the premise of ensuring quality, complete or ahead of schedule the progress of sub-projects or the control progress of major projects.
3, engineering safety benefits:
(1) The safety organization network is sound, and all employees have a strong sense of safety. Safety regulations and safety measures are implemented, and potential safety hazards and irresponsible casualties or engineering accidents are eliminated in time.
(2) Strictly implement the bidding system for equipment and materials procurement to ensure the quality of materials and put an end to corruption.
(3) Strictly control the project investment, reduce the cost and consumption, and achieve remarkable results.
Detailed rules for the implementation of verbs (abbreviation of verb)
1. Strengthen leadership and elaborate organization: all construction sections are required to put this special labor competition for quality and safety on the important agenda, improve the leading organization and work team of the competition, and form a working situation in which the "top leader" personally takes charge, all departments actively cooperate, and quality, safety and construction are jointly managed.
2, clear objectives, highlight the key points: the construction unit is required according to the overall goal of the competition.
And determine the competition objectives according to their respective tasks, establish the competition focus and theme according to the actual situation and characteristics of construction blocks, put forward specific standards and rules for different stages and different assessment objects, and formulate specific plans for labor competition.
3. Extensive publicity and launching at different levels: the construction unit is required to take various forms, conduct in-depth publicity and mobilization, and clarify the significance, contents, practices and requirements of labor competition for the construction of this project, as well as the goal of carrying out competition activities in this construction bid section, so that everyone can know and participate actively.
4. Cultivate typical examples: In carrying out quality and safety special labor competition activities, we should pay attention to cultivating typical examples and use them to open the way. At the same time, it is necessary to discover, cultivate, select and publicize the advanced models actively presented in the competition activities in time, so that the advanced models can have a group effect to promote the project construction.
5. Strengthen supervision and strict assessment: members of the supervision team and all construction sections should strengthen the supervision and inspection management of the whole process of the competition, establish ledgers and conduct regular assessment and inspection. Check, compare and summarize by stages.
Six, assessment and reward:
According to the contents of the document [20 12] 12 issued by the project management office of the waterway regulation project construction headquarters in Dongtai section of Shen Lian Line in Yancheng City and the relevant provisions of the small economic reward and punishment system in construction management, the QLSG 1 bid section, QLSG2 bid section and QLJL bid section involved in the project construction were assessed. Bid blocks, construction teams and advanced individuals with outstanding performance in the construction of quality and safety special labor competition activities in this bid block are recommended by each bid block and reported to Dongtai section of Shen Lian Line by the supervision team.
Waterway regulation project office. Reward the advanced collectives and individuals emerging in the assessment. Personnel who are irresponsible and dereliction of duty shall be punished in accordance with the reward and punishment system for small-scale economy in construction management. If the circumstances are serious, it shall be dealt with severely according to relevant regulations.
In short, through the special labor competition for quality and safety, we should achieve the work requirements of "zero defects in engineering quality, zero accidents in production safety, zero corruption in engineering integrity and zero pollution in bridge construction", further enhance the sense of responsibility, strive for the first place, innovate and start businesses, and strive to achieve the qualified rate of sub-projects 100%, the excellent rate of unit projects 100% and safety. Build the waterway regulation bridge project of Dongtai section of Shen Lian Line into the "Yangtze Cup" project.
Jiangsu Taikang engineering consulting supervisory co., ltd
LSX-DT-QLJL supervision team
20 12 July 28th