A new skill training building in a vocational and technical college is all invested by the government. The project has been included in the local annual fixed investment plan, and the design and construction drawings of the project have not yet been completed, and the relevant technical data have not yet been compiled. In order to make the project completed and put into use as soon as possible, the construction unit decided to bid for the project. Because it is estimated that in addition to the construction enterprises in this city, there may be enterprises from other provinces participating in the bidding, in order to make the construction enterprises in this city have the bidding advantage and control the enterprises from other provinces to participate in the bidding, the bidding enterprises are required to have the construction experience of similar projects in this city in the past two years. On June 5th, 2008, the construction unit sent the bidding invitation letter to contractors A, B, C and D4 who have the ability to undertake the project, stating that the bidding documents were collected in the infrastructure room of the logistics management office of the tenderee on June 22nd101,and the deadline for bidding was June 22nd 17. After the tender documents were issued, a tender preparation meeting (Q&A meeting) was held on June 14, and the questions raised by the tenderer were answered in writing. On June 16, the bidder was organized to conduct a site survey. Before June 22nd 17, all the above four bidders submitted their bids.

Question:

(1) Does this project meet the requirements of construction bidding, and is the way of construction bidding appropriate?

(2) What's wrong with the bidding documents? If so, what are they?

(3) What's wrong with the bidding work and what's the correct way to do it?

Answer:

(1) Does this project meet the requirements of construction bidding, and is the way of construction bidding appropriate?

Answer: This project does not meet the requirements of construction bidding, and the construction bidding method is inappropriate.

Cause analysis:

① The funds for government investment projects have not yet been implemented;

(2) Engineering design and construction drawings have not been completed, and relevant technical data have not been compiled;

(3) Government-invested construction projects must adopt public bidding.

(2) What's wrong with the bidding documents? If so, what are they?

A: There is something wrong with the tender documents. It mainly includes: adopting local protectionism, setting conditions to restrict enterprises from other provinces to participate in bidding, and requiring bidding enterprises to have construction experience of similar projects in this city in the past two years in the bidding documents; There is no clear way and content of qualification examination of bidding enterprises; The specific bid evaluation method is not clear.

(3) What's wrong with the bidding work and what's the correct way to do it?

A: Open bidding should be adopted; The time from issuing the tender documents to the deadline for bidding is less than 15 days; Bid preparation meeting (question and answer session), giving written answers to the questions raised by bidders, but failing to provide written answers to all bidders; The bid opening time is not clear, that is, the deadline for bidding is June 22nd 17.