What are the procedures and steps for the post-renovation of blank houses? For example, decoration, ceiling, wall approval, plumber,
First of all, it is generally the most time-consuming for carpenters to enter the site for decoration, including the erection of ceiling keel and the production of wooden doors and windows, which generally takes 20 days.
Then let carpenters make wooden partitions and ceilings, and masons can also build walls at this time, and the two work together.
Generally, it only takes 1 day to install the window.
After the woodworking stage is completed, there will generally be a door cover size, and the wooden door can be customized according to the door cover size.
Next, it's time for the masons to work. At this time, it is necessary to pile up yellow sand, bricks, cement and waterproof paint at home. At this time, the clay trade union will inform you of the area of floor tiles and wall tiles. After the materials for purchasing ceramic tiles in Building Materials City are in place, it is necessary to start laying ceramic tiles, including waterproof works, installation thresholds, ground keels, etc., which are all completed at this stage.
The size of the kitchen has been obtained on it. At this time, it is necessary to confirm the final kitchen design scheme, including sink and gas stove. , as well as the size of the washing machine and refrigerator, so that workers can maintain a good posture; The water heater and shower room needed for the bathroom should be determined.
Next, it is time for furniture to enter the market, including wardrobes and porch cabinets.
The door should be installed after the furniture enters the site, in case the furniture is too big to enter the site.
Painters usually scrape putty and paint when they enter the site, which usually takes half a month.
Installation of water heater and gas pipeline. The gas pipeline must be tested after installation, and if there is any problem, you can ask for rework.
When installing the ceiling of the kitchen and bathroom, remember to ask the master to lay the shelves needed for the installation of Yuba. This is very important and should be remembered.
If there are old walls at home, you need to shovel one side of the wall. This step is operated by the painter. If the wall is found to be loose, it should be handled in time, and then the cement is laid.