Example 1 of the extension application report: Extension application report

To: Weixi Housing and Urban-Rural Planning and Construction Bureau

Weixi Lishui Rongcheng Real Estate Development Co., Ltd.

Yunnan Keyu Construction Supervision Co., Ltd.

Thanks to the Weixi Housing and Urban-Rural Planning and Construction Bureau for its trust and support to our company. The "Weixi Li Water Integration Phase I Project" is under construction.

However, after my project department entered your construction site, the following problems seriously affected the normal construction and progress plan of our project:

1. The number of power outages in Weixi County was too high Many, from the start of construction on July 18, 2013 to now

The total power outage time is 6 days;

2. The rainy season weather is 26 days.

3. Impact of the Spring Festival holiday:

Since January 30, 2014 is New Year’s Eve, the Spring Festival holiday will last until February 10, which will affect the construction period by 15 days;

IV. When the temperature drops, concrete pouring can only be arranged during the day as much as possible, and no arrangements are made at night

The overall construction time is reduced by half, causing a direct impact;

The above four items have been Due to the delay in the construction period of this project, in order for the construction and development of Weixi County and the Lishui Rongcheng Phase I project of Weixi Lishui Rongcheng Real Estate Development Co., Ltd. to be completed as scheduled according to the total construction period, our project department has now based on the geographical and natural climate environment of Weixi County We have prepared a winter construction plan based on the conditions and submitted it to the supervisor and Party A for approval. We also ask your bureau to review whether the content prepared by our contractor can meet the construction conditions. The application time is 50 days. We hope that the leader will give verification and approval. Thank you!

Applicant unit: Diqing Construction Engineering Group Guangmao Engineering General Contracting Co., Ltd.

Date: Weixi Lishui Rongcheng Project Department of Ren Company? December 1, 2013 Part 2 : Extension application report

Extension application report

To: Henan Xindu Industrial Co., Ltd.

My unit Urban Construction and your company's Xindi Technology Plaza scientific research and design comprehensive The fire protection project of the building has been completed according to the drawing design requirements. Due to some objective factors, the contract delivery date was delayed. We now report the factors that caused the construction delay to your organization as follows:

1 Factor 1: On November 15, 2010, we organized workers to enter the site according to your request○

Construction started, but When we entered the site, the general contractor's main body, secondary structure and painting portion had completed less than 50% of the work, and there was no working surface for our construction, causing our construction personnel and machinery to be stagnant until April 2011. Only when the working conditions basically meet the construction requirements.

2 Factor two: ○The change in the practical functions of your scientific research complex has made construction more difficult for us. Room spraying and secondary decoration increased the workload and difficulty of the work. By June 2011, the construction and suppression of our spray pipes had been completed. However, due to the aesthetic requirements of the decoration, we need to cooperate with the decoration. From June to September 2011, our construction workers basically sacrificed our precious time to meet the decoration schedule.

3 Factor three: ○Due to the ceiling decoration work, our alarm line’s embedded pipe was interrupted, which greatly increased the workload and difficulty of wiring, causing our cost to increase and the construction period to be delayed by nearly 2 months. .

4 Factor 4, ○ Impact of cross-working of multiple types of work: There are nearly 30 construction teams in the comprehensive building entering the decoration stage, and the working surface is relatively concentrated, which reduces the loading of construction materials and the construction efficiency of workers. effect phenomenon. The construction elevator of the general contractor is far from meeting the construction requirements.

5 Factors 5: The impact of fire water tanks, voltage stabilizing devices, and external networks on our work. ○

1. You also attach great importance to the transportation of fire water tanks and voltage stabilizing devices. After inspection and comparison, we will organize the transportation and production. The period is long and the installation work between fire water tanks is lagging behind. , the system suppression work becomes more difficult.

2. It was not until May 2012 that your external network had water connections. The overall system debugging of the scientific research building can be carried out.

In summary, we hope that the leaders of your organization will understand and help us with our actual situation. We are also deeply aware of the shortcomings and deficiencies in the construction management process. I also ask for criticism and understanding from your leadership for failing to communicate and report to the owner in a timely manner. Understand the delay in our construction period and help us with our difficulties.

2012.07.07 Part 3: Continuation Application

Applicant:

Application Date:

Dongguan Food and Drug Administration Preparation

Instructions for filling in

1. This application form is to be filled in by the applicant. Use a carbon pen or print when filling in. The text must be concise and clear, and there must be no alteration. Fill in the blanks with the word "none".

2. "Applicant" refers to the unit or individual applying for a catering service license, and shall be filled in according to the name approved by the industrial and commercial administration department.

3. Economic nature includes: state-owned economy (domestic capital), wholly state-owned, collectively owned, joint-stock cooperative enterprise, joint venture, limited liability company, joint-stock company, private enterprise, other domestic-funded enterprise, Hong Kong , Macao and Taiwan investment enterprises, joint ventures between the Mainland and Hong Kong, Macao and Taiwan, cooperation between the Mainland and Hong Kong, Macao and Taiwan, sole proprietorships from Hong Kong, Macao and Taiwan, Hong Kong, Macao and Taiwan investment companies, other Hong Kong, Macao and Taiwan investments , foreign investment, Sino-foreign cooperation, foreign investment, foreign investment joint stock company, sole proprietorship, partnership, other foreign investment, individual economy, others, etc.

4. Total business area: total area of ​​catering processing business premises, tourism, foot massage, and recreation. ?Catering processing and business area: refers to the area of ​​places directly or indirectly related to food processing and business, including food processing area, dining area and non-food processing area (referring to offices, changing places, foyers, lobby lounges, Areas that do not directly handle food, such as singing stages, non-food warehouses, bathrooms, etc.). ?Food processing area area: refers to the total area of ​​Chinese kitchen, Western kitchen, and other kitchens (such as Japanese and Korean kitchens, etc.), including rough processing, cutting, cooking and meal preparation places, special rooms, Disinfection area, cooking area, food warehouse. ?Dining place area: refers to the place for consumers to eat (including Chinese, Western, Japanese food halls and rooms). ?Declared maximum number of people serving meals: refers to the maximum number of people that can be served for one meal, not equal to the number of seats.

5. To fill in the "Application for New License Project", you should check the corresponding application items in the corresponding category and remarks column. If the applied item is not within the listed range, check the "Other" item , and fill in the specific content.

6. If the form cannot be filled in due to too much content, please follow the page.

7. This application must be made in duplicate.

;