Scaffolding construction scheme of drainage pumping station?

What is the scaffolding construction method of drainage pumping station? What are the methods? Please read the article edited by Zhong Da Consulting Company.

Scaffolding construction scheme of drainage pumping station

I. Overview

The structural shape of this project changes greatly, and the plane is zigzag. The main building is 1 1 floor, and it is planned to adopt floor-to-floor double-upright scaffolding and channel steel cantilever frame for erection.

Second, the plane layout

According to the characteristics of building plane, φ 48 steel pipe is used for engineering scaffolding. The vertical distance of the vertical pole of the shelf is 1.5M, the horizontal distance of the vertical pole is 1.00M, the step distance is 1.75m, and the inner pole is 250MM away from the wall. The shelf connection at the construction elevator should be set up separately, so as to facilitate the construction after the outer frame is dismantled in the decoration stage.

Third, basic treatment.

The foundation within the scope of scaffolding shall be compacted, leveled, hardened and well drained. Full-length 10# channel steel shall be set at the bottom of the vertical pole to evenly transmit the concentrated force of the scaffold, and a sweeping rod shall be set 200mm away from the bottom to maintain the integrity of the scaffold bottom.

Four, the main safety technical measures

(1) The embedded parts such as cantilever steel pipes shall be embedded in time according to the drawings.

(2) Steel pipes shall be genuine, free from concave-convex shapes, defects, cracks and deformation, and have factory certificates; The joint surface between the fastener and the steel pipe should be in good contact, and there should be no cracks, pores, porosity, sand holes or casting defects that affect the service performance.

(3) Each floor is provided with wall connecting pieces, which are arranged in a quincunx shape every 6m (four longitudinal distances) and every floor (3.2-4M). The wall connecting rod is embedded with Ф10 round steel, and welded with the steel pipe on the shelf (welding length is 5CM).

(4) The bracing should be set with the scaffold at the same time, the spacing should be controlled within 9M and the angle should be 45.

(5) Scaffolding must be higher than the construction operation surface 1.8M (one step), and be enclosed with scaffolding with a height of 1M and a dense mesh safety net, and be closed with bamboo veneer or bamboo basketry every four steps away from the wall.

(6) The protruding end of each bar should be greater than 100㎜.

(7) Cable-stayed round steel is tightened with basket bolts, so that the tightening degree of all Rachel is basically the same, and the uneven stress is reduced. The lifting point must be at the intersection of the vertical rod, the main rod and the small rod, and the bottom of the pull rod should be tightened.

(8) Before scaffold erection, safety technical disclosure shall be conducted, and the operators must hold relevant certificates and strictly abide by safety regulations and operating procedures.

(9) Hang it on the shelf as required for emergency use.

(10) grounding and lightning protection shall be done in the conventional installation section, and the steel pipes and structural steel bars of the cantilever frame shall be welded for lightning protection at the corner and middle of the frame, and the grounding resistance shall not be greater than 4Ω.

Five, shelf maintenance and acceptance

(1) Scaffolds shall be accepted before being put into use.

(2) The Quality & Safety Department of the company shall organize the person in charge of the construction site, technical, safety, installation and other related personnel to conduct the acceptance together. After acceptance, an acceptance form shall be filled in and signed by the person in charge of the construction site and the acceptance personnel. Only after the acceptance is qualified can it be put into use.

(3) Scaffolding shall be inspected by the site safety officer and the shelf team leader, and shall be inspected regularly by the company's Quality and Safety Department, and handled in time when problems are found.

(4) It is forbidden to concentrate building materials such as steel pipes and molds on the external scaffolding. Major design changes such as formwork support must be approved by the competent technical personnel, and can only be used after the written procedures are completed.

Six, shelf demolition

(1) When the shelf is dismantled, the operation area should be divided, warning signs should be erected around it, and the ground should be commanded by special personnel. Non-working personnel are strictly prohibited from entering.

(2) Dismantling aerial workers must wear safety helmets, fasten safety belts, tie their legs and wear soft-soled shoes.

(3) The demolition sequence should follow the principle of top-down, first erection and then demolition, and proceed in turn according to the principle of one step in place. It is strictly prohibited to carry out demolition work at the same time.

(4) When dismantling the upright post, hold the upright post first, then dismantle the last two buttons, dismantle the main rail and diagonal bracing, dismantle the middle button first when bracing, then hold the middle button and untie the end button.

(5) Even the wall pole should be dismantled step by step with the demolition progress.

(6) When dismantling, there should be a unified command, echoing up and down, and coordinating actions. When you untie the knot related to others, you should inform the other party first to prevent it from falling.

(7) Before dismantling the big shelf, the reserved chute, feeding platform and small flying channel should be reinforced to ensure the integrity, safety and stability after dismantling.

(8) Be careful not to damage doors, windows, glass, etc. When disassembling.

(9) The dismantled materials shall be bound by ropes and transported slowly by pulleys. Do not throw them. Materials transported to the ground should be placed in the designated place, transported with the demolition, and stacked in categories. The removed fasteners should be collected and disposed of centrally.

(10) During the demolition process, it is not allowed to change people in the middle. If it is necessary to change people, the dismantling situation should be explained before leaving the company.

(1) drilling

Put the used drilling rig on the designed hole position so that the drill pipe is aligned with the center of the hole position. After the drilling rig is in place, calibrate the fuselage with a spirit level, so that the drill pipe axis is vertically aligned with the drilling center, so as to ensure the verticality of the drilling hole to meet the design requirements. The hole position deviation is not more than 5 cm. In fact, each hole should have measured elevation and coordinate records, and the hole depth and aperture should meet the design requirements.

Borehole inclination is measured during drilling. The borehole inclinometer adopts KXP- 1 portable inclinometer produced by Shanghai Geological Instrument Factory, which is convenient to operate. The measurement results can be directly observed from the dial of the operation box, and the accuracy can meet the requirements of engineering use. Because the outer diameter of the borehole aperture ratio instrument is relatively large, in order to make the measurement results true and accurate, guidance is provided during borehole measurement. The inclinometer is installed in the guide tube, concentric and coaxial with the guide tube (the length is 3.5-4.0m, and the outer diameter is the same as that of the drilling tool). The vertical deviation shall not be greater than 65438 0.5%, and shall meet the requirements in the following table:

Hole depth m2030405060

The allowable deviation is m0.250.450.701.005438+0.3.

In order to ensure the verticality of drilling, the following points should also be done.

The drilling rig is equipped with a base to keep the drilling rig stable when it works.

After the rig is in place, it should be stabilized and adjusted to keep the rig vertical.

Check the verticality of vertical shaft at any time, add long-diameter drilling tools, and prohibit the use of bent drill pipes and bent large-diameter drilling tools.

Short drilling tools shall not be used except for drilling, and the length of drilling tools shall be kept above 3.5m, and drilling parameters shall be used reasonably during drilling.

Measure the well deviation every 5- 10m, and detect the drilling process. If the well deviation is large, effective measures should be taken in time to correct the well deviation (such as tripping drilling tools for repair, hole filling and reaming, etc.). ). When the drilling operation is temporarily terminated, the orifice shall be properly protected to prevent sewage from flowing into the orifice and foreign matter from falling into the orifice.