Those who know how to decorate come in and have a look Who can tell me the decoration process?
1. foreman, designer, owner, on-site disclosure
2. Check and complete the handover, preferably with a written receipt signed by both parties.
3. The owner to the property for construction permits, open water and electricity.
4. Inform the balcony to make on-site measurement.
Decoration Day 2
The decoration team will demolish the wall, original facilities and holes, demolish the wall skin, clean up the site and remove the garbage as planned.
Decoration Day 3
Hydropower positioning and material approach
decorate
Day 4-5
Notify the floor heating manufacturer to enter the site for construction.
decorate
Day 6-15
1. Hydropower materials enter the site for construction, waterway pressure holding test, and waterproof materials enter the site.
2. Notify fresh air manufacturers of central air conditioning to enter the site for synchronous construction.
3. Hardware, faucets, showers, angle valves, hoses, etc. shall be purchased, and the plumber shall count the quantity and be present 3 days before the bathroom installation.
4. Buy mirrors and mirror cabinets and be present 3 days before installation.
5. The shower room is reserved, and the bricklayer will conduct field measurement after completion.
6. The quantity and model of lamps and switch panels shall be counted by plumbers and shall be present 3 days before installation.
Decoration Day 16- 19
1. Waterproof construction, closed water test
2. Inform the floor tile delivery, and make an agreement with the foreman to let the foreman receive the goods.
3. Balcony sealing manufacturers enter the site for construction.
Decoration Day 20-30
1. Tile laying, stone laying, pipe wrapping and ground leveling.
2. After the bricklayer comes into play, measure the wooden door and start making.
3. The bricklayer shall notify the cabinet after completion, and the manufacturer of the basin cabinet will start production after field measurement. Window sill stone, window sill stone, shower room water stop, purchased after field measurement.
4. After the bricklayer's floor and skirting line are completed, the total amount shall be measured and calculated at the site.
Decoration day 3 1-36
1. The balcony ceiling, wallboard, soft and hard bag base and door opening of the guest dining room are illuminated.
2. Notify integrated ceiling manufacturers to install synchronously, measure wallpaper and wall covering on site, measure wardrobe manufacturers on site, produce and measure shower room manufacturers on site, and produce.
Day 38-46 of renovation
1. The top surface of the wall is treated at the grass-roots level, gypsum line is installed, putty is scraped, latex paint is brushed or wallpaper is pasted.
2. Inform the wooden door to install, and install the door after the putty is completed twice. Doors need finished product protection.
Day 47-49 of renovation
1. Notify the cabinet 3 days in advance, and the cabinet manufacturer will install it.
2. Notify the kitchen appliance 3 days in advance and install the sink on site.
The 50th day of renovation.
Install basin, toilet, bathtub, faucet and shower, all materials include angle valve, hose, etc. Three days in advance.
Decoration day 5 1
The floor manufacturer will inform you one week before installation.
52-54 days of renovation
The wardrobe manufacturer will inform you of the installation one week in advance.
Day 55-60 of renovation
1. The installation of hardware, lamps, switch panels, mirrors, mirror cabinets and materials shall be delivered 3 days in advance.
2. The shower room shall be installed by the manufacturer and notified 3 days in advance.
3. Acceptance and maintenance