Simplified earthwork contract

In today's developing world, contracts are more and more widely used, and signing contracts can prompt both parties to promise and perform cooperation in a standardized way. So how to write a detailed contract? The following is a simple version of the contract template for earthwork contracting (selected 6 pieces) carefully arranged by me. Welcome to share.

Simplified earthwork contract 1 Party A:

Party B:

According to the Contract Law of People's Republic of China (PRC) and other relevant laws and regulations, combined with the actual situation of the construction site. In order to clarify the rights, obligations and responsibilities of both parties, the following agreement is reached through consultation.

Chapter I Overview of Contracted Projects

1. 1 project name: coal-soil separation in open-pit coal mine

1.2 Project location: Duan Chun Town, Lingshi County, Jinzhong City, Shanxi Province.

1.3 project content: earthwork transportation (including soil, stone, coal, slag, etc. ).

1.4 project quantity: 20 million cubic meters.

1.5 contract period: from MM DD YY to MM DD YY.

Chapter II Construction Equipment, Personnel and Materials

2. 1 The transport vehicle model of Party B shall be a double-bridge dump truck with a load of more than 290 horsepower.

2.2 Party A must provide Party B with maintenance sites, electricity, accommodation and domestic water facilities required for construction and transportation, and ensure the safety of Party B's personnel and equipment.

2.3 Party B must manage and maintain the water, electricity and facilities provided by Party A. ..

Chapter III Responsibilities of Both Parties

3. 1 Party A is responsible for coordinating the relationship between all units in the mining area and creating convenient conditions for Party B's smooth transportation. Party A must assign professionals to be responsible for road leveling every day to ensure that Party B's loading and unloading operation surface is free from traffic jams and keep the road smooth.

3.2 After Party B's vehicles enter the site, 2-3 drivers with more than 3 years' driving experience must be arranged to operate the dump truck. Make sure it is safe and normal.

3.3 When vehicles enter the construction site, they must strictly abide by the road traffic laws and regulations, and must also abide by the company's various rules and regulations. Drive with low speed, safety, caution and civilization, abide by safety laws and regulations, operate in strict accordance with the requirements of on-site management personnel, obey the command and dispatch of on-site management personnel, and it is forbidden to drink and drive, wear slippers, barefoot and shirtless. No luxury cars, luxury cars.

3.4 Vehicles shall be hauled and dumped at the designated place during engineering operation. Those who do not follow the requirements, listen to the command and obey the management will be dealt with severely once verified. However, Party A must clearly indicate the signs and shall not give orders in violation of laws and regulations.

3.5 Dump trucks are not allowed to steal oil, coal or bribe management personnel during construction, and management personnel are not allowed to ask for bribes, eat, take, get stuck or demand from drivers and staff.

3.6 If there is a fight now, once it is found, it will be handed over to the public security organ for handling, and the consequences will be at your own risk.

3.7 In case of work stoppage due to weather and normal construction conditions, Party B must drive the vehicle to the construction site as soon as possible after receiving the notice, and shall not delay the time for any reason.

3.8 Party B shall attend the regular safety production meeting of Party A on time. The related safety operation accumulation conveyed by the safety meeting shall be strictly implemented in each post. If traffic accidents collide with each other, they shall protect the site and report to Party A in time, and all expenses shall be borne by both parties. If Party B violates safety operation and accumulates various accidents, Party B shall bear all legal responsibilities and all economic responsibilities, and Party A shall be responsible for any fault caused by Party A's reasons. ..

3.9 The volume of the carriage shall be subject to the measurement of Party A's management personnel. If the moped is smashed, it should be repaired in time. If it is not reported and not repaired in time, the number of volumes in the current month shall be calculated according to the number of volumes that have not been increased. If you want to add plateau carriages, you must apply to the company for approval three days in advance, and the heightening materials must meet the safety standards, otherwise the heightening part will not be counted. The quantity after heightening shall be subject to the quantity re-measured on the same day. During off-duty, the residue adhered in the carriage should be cleaned up in time.

3. 10 During the contract period, if Party B stops work, exits or only does earthwork without earthwork, it must notify Party A fifteen days in advance, and then it will be decided by both parties through consultation.

3. 1 1 During the construction at night, the driver of Party B shall not stop to sleep. If he needs a rest, he must ask for leave from the site management and rest at the designated place. Take a break without authorization, be punished as absenteeism and be fined. If Party A forces the driver to drive fatigue, the consequences shall be borne by Party A..

3. 12 If the excavator stops working or the loading is slow due to Party A's reasons, Party A shall be informed first. If the urgent problems are not solved, Party A shall compensate Party B for each vehicle per hour 100 yuan.

Chapter IV Measurement, Settlement, Unit Price and Payment Method

4. 1 The excavation and transportation price is RMB per vehicle, and the transportation price is based on the transportation distance of 2,000 yuan per cubic meter. For every additional distance of 100 meters, the per cubic meter 1 yuan is added to the basic price. The traffic volume of each vehicle should not be less than square meters, and each additional party will increase the cost by RMB per square meter. The volume calculation method is based on the vehicle volume (length× width× height), and every liter of diesel oil is guaranteed, which is not affected by the market price increase. The fuel cost of transport vehicles shall be settled together with the monthly project payment. The above freight price includes the comprehensive price of the top and bottom earthwork and fuel costs, as well as all expenses including the driver's salary and machinery. In case of fuel price increase, increase the man-machine fee and then make up the difference.

4.2 Payment Method

After vehicles enter the site, each vehicle will pay 2000 yuan, and the excavator will pay 7000 yuan, which will be deducted in the first month. The date of each month is the date of ticket inspection and settlement. After Party B's vehicle arrives at the site for trial pulling, it is estimated that 30% of the project cost will be paid in advance every 65,438+00 days, and the rest will be settled together after ticket inspection. If the settlement cannot be made on this deadline due to bank reasons or Party A can explain justified reasons, it will be subsidized by 3% of the total interest. Party A shall settle the project payment on time. Otherwise, Party B has the right to stop and wait for settlement. If Party A fails to fulfill its promise, Party B has the right to stop and wait for Party A to settle the payment. Party A shall bear the subsidy of 2000 yuan per vehicle.

4.3 After both parties sign the contract, Party A will provide living expenses and car repair expenses in RMB, and return them to Party A after the contract expires.

Chapter V Modification and Termination Clauses of the Contract

5. 1 When the execution of this contract is affected by force majeure factors such as superior government and bad weather, the contract term can be terminated or postponed after confirmation by both parties, so the losses caused to Party B shall be compensated.

5.2 After the expiration of the contract, both parties to the contract will automatically terminate the relationship. If Party B can strictly perform this contract, after the expiration of the contract, Party B has the priority to contract under the contract conditions.

5.3 If there are any matters not covered in the execution of the contract, both parties can solve them through negotiation. If negotiation fails, the lawsuit can be decided to the people's court of Hubin District, Sanmenxia City.

Party A:

Party B:

Date of signing:

Simple earthwork contract 2 Party A:

Party B:

In accordance with the Contract Law of People's Republic of China (PRC), Regulations on Safety in Open-pit Mining, Law on Safety in Production, Law on Mine Safety, Code for Acceptance of Open-pit Mining Projects and other relevant laws and administrative regulations, and following the principles of equality, voluntariness, fairness, honesty and credibility, the following agreement is reached and both parties shall abide by it.

I. Overview of the Project

1, project name: earthwork stripping project of Chagan Fulu silica mine in Siziwangqi.

2. Project location: Chagan Fulu silica mine in Siziwangqi.

3. Project content: stripping, excavation, loading, transportation, leveling, road construction, watering, maintenance and mineral processing of earthwork in the mining area. Not responsible for greening.

4. Engineering quantity: measured according to actual quantity.

Start date: year month day. (Subject to Party A's notice of entry)

Total construction period: two years

Second, the project model and valuation

1. Mode of cooperation: six packages (including labor costs, materials costs, machinery costs, oil costs, living expenses and repair costs).

2. The transportation distance is less than 2 kilometers. (Not including the distance between the starting line and the safety line)

The depth is 40 meters, which is 40 meters below the horizon. (If the depth exceeds 40m and the transportation distance is 2km, the expenses shall be calculated according to the quota standard for compensation. )

4. Unit price of earthwork: RMB/m3.

5, yuan/cubic meter. (The above unit price includes the after-tax price of digging, loading, transportation, leveling, road construction, watering, maintenance and ore classification).

Three, the basic requirements of engineering survey and construction:

1, measured by a natural party signed and recognized by both parties after surveying and mapping.

2. The measurement of engineering quantity is calculated by drawing software 10MXIOM grid.

3. After receiving the notice from Party A, Party B will enter the site on time to build temporary facilities (the site will be designated by Party A, and the expenses for building temporary facilities will be borne by Party B). According to the actual situation of the construction site, Party B will dispatch mechanical equipment according to Party A's plan. Party B shall not dispatch machinery and equipment to the site at will, and all consequences arising therefrom shall be borne by Party B.. Party B's own machinery and equipment shall not be less than 30% of the total machinery and equipment, and the machinery and equipment shall be in good condition, with an operating rate of over 90%. Ore grading shall be organized by Party B according to the requirements of engineering mineral processing, and Party A has the right to supervise all construction procedures of grading operation.

4. Party B shall ensure the quality of mining construction, strictly control the quality of ore, and stack it in strict accordance with the quality classification, and shall not dispose of ore and other ancillary products without permission.

5. Party B shall provide Party A with the construction organization, safety measures and personnel organization chart before entering the site, and carry out the construction according to the drawings or construction plan provided by Party A. ..

6. During the construction, Party B must strictly implement and abide by Party A's rules and regulations, safety standards, construction and other related systems. Before Party B's personnel and machinery enter the site for construction, Party A shall conduct pre-job safety training for on-site construction personnel and machinery operators, and sign a safety guarantee with Party A, otherwise the losses caused thereby shall be borne by Party A..

Fourth, the settlement method:

1. Party B shall submit the bill of quantities to Party A on the 25th of each month according to the signed quantities actually measured by both parties. After being audited by Party A, 80% of the project payment shall be paid before the following month 15, and the remaining 20% shall be used as the safety deposit, and paid in full every month after three months. In case of legal holidays, it will be postponed for one week.

2. Settlement basis: The project payment shall be settled by the "Bill of Quantities that passed the acceptance after Party A and Party B signed it into effect".

3. Party B authorizes the designated payer and holds the power of attorney of all mechanical equipment and construction personnel for settlement (payment by credit card or cash check).

4. When this Agreement is signed, Party B shall pay the mortgage risk to Party A, with a total amount of RMB (in words: ten thousand yuan).

5. Party A shall arrange management personnel and mechanical equipment to enter the site according to Party A's plan within seven days from the date of receiving Party A's notice of entry. If Party B fails to arrange management personnel and mechanical equipment to enter the site according to Party A's plan within seven days, otherwise Party B will be deemed to have breached the contract. The penalty is 20% of the mortgage risk as compensation, and Party A has the right to terminate this agreement. If the project fails to start as scheduled, Party A shall pay the mortgage risk to Party B after 90 days, and compensate the losses caused by it according to the standards stipulated in the Mine Production Contract Law. If the production is stopped or stopped due to Party A's reasons, the excavator shall pay 65,438 yuan+0,000 yuan per day, the dumper shall pay 500 yuan, the loader shall pay 500 yuan, and the worker's salary shall pay 65,438 yuan+0,000 yuan per day.

6. Party A shall go through the examination and approval procedures required by the local government, public security and safety supervision departments.

7. Except for the matters agreed in the General Terms and Conditions, Party A has nothing to do with irresistible natural and policy factors, such as national high temperature, cold, rain, snow and flood policy changes, local government affairs and safety inspection.

Verb (abbreviation of verb) Rights and obligations of Party A:

1. Party A is responsible for external coordination during the construction period, and coordinating the relationship with the local government and village communities, so that Party B can have a good construction environment and ensure the smooth progress of Party B's construction. ..

2. Party B shall bear the costs of temporary construction site, lighting and water and electricity interface provided by Party A. ..

3. Pay the project payment according to the terms of the agreement.

4. Party A shall pay Party B the project payment, and the unit price shall include the safety production expenses.

5. Party A has the right to cooperate with Party B and dismiss any member of Party B whose ability or behavior is considered by Party A to be incompetent for relevant work in this field.

6. Party A can provide necessary help and support and cooperate with Party B to complete various tasks. Party A shall give corresponding guidance to the construction quality, and may supervise and inspect at any time. If Party B fails to carry out the construction according to the operating rules and construction specifications of ore grading technology required by Party A, resulting in waste of quality and rework, Party B shall compensate all losses caused thereby.

The rights and obligations of party b with intransitive verbs

1. According to the regulations of Siziwangqi Safety Supervision Bureau and relevant departments, the contractor must have the qualification above Grade II for earthwork engineering and hold three certificates (project manager certificate, engineer certificate and safety officer certificate); Otherwise, it is not allowed to enter the site for construction.

2. Party B shall organize the construction seriously, scientifically and reasonably according to Party A's construction schedule to ensure that the monthly schedule is completed on time.

3. Party B guarantees that it has the conditions for safe production and construction stipulated by laws, regulations, rules and standards, and its staff must hold valid work permits and operation certificates.

4. Party B shall cooperate with Party A in the inspection and acceptance of safety production management.

5. Project quality requirements: Party A and Party B shall determine the construction standards after research, and Party A shall supervise Party B's construction as required. In case of illegal construction by Party B, Party A shall require Party B to stop work for rectification. If Party B still fails to meet the construction standards determined by both parties after rectification, Party B shall bear the import and export expenses of all equipment and personnel, and both parties shall not bear the responsibilities, and this Agreement shall be dissolved.

6. Party B shall be responsible for all safety work within the construction scope and have adequate safety guarantee measures. Civilized construction, strictly abide by mine safety laws and regulations. All responsibilities (including legal responsibilities and economic responsibilities) for all safety accidents that occur within the scope of Party B's work or life shall be borne by Party B. ..

7. Party B shall strengthen the management of its subordinate personnel, and shall not employ persons who violate the law, have no valid identity documents or are unidentified. Party B shall actively cooperate with Party A to do a good job in comprehensive management, prevent the occurrence of criminal cases, and strictly control the occurrence of fighting, gambling, alcoholism, drug abuse, theft and robbery. Anyone who enters the construction site must wear a safety helmet. Whoever is found not to wear it will be fined Wu Bai dollars.

8. Party B must submit to Party A the payroll of laborers and the settlement statement of mechanical equipment lease every month, which will be reviewed by Party A and issued by Party A's financial supervision.

Party A:

Party B:

Date of signing:

Simple earthwork contract 3 Party A:

Party B:

According to the provisions of the transportation contract of stripping project signed by XXX Co., Ltd., Party A and Party B reach the following agreement through consultation:

I. Responsibilities and obligations

1. Party A is responsible for providing the construction site for stripping earthwork, providing accommodation for construction personnel, vehicle maintenance and vehicle refueling. The above expenses will be deducted from Party B's project payment at the end of the month.

2, in the construction of mechanical equipment, operating machinery and equipment personnel must hold relevant certificates.

3. Party B's operators, vehicle drivers and excavator workers must have insurance, otherwise the consequences of the accident will be at their own risk. Personal safety, vehicle accidents, etc. Should be borne by the individual).

4. As for the equipment requirements, the excavator must be more than 360, and the standard of the dumper is (5.6m× 2.3m× 1.5m), which can be used as a garage, 20m3 (the construction period is tentatively set at two years).

5. The requirements for excavators must be in accordance with Party A's engineering requirements, so as to be smooth, level and tidy. It must be loaded according to Party A's requirements, and the fines arising therefrom will be borne by you.

Second, the distance, unit price and settlement method

1, the transportation distance is 0-3.5km, the digging depth is not more than 40m, the vehicle marshalling ratio is 1: 6 as a group, one excavator is 97 yuan and the other is 38 yuan.

2. Monthly settlement: the quotation will be settled on 25th of each month, and the settlement will be made on 10 next month.

Three. Requirements and systems

1. The operator of Party B shall obey the command. If they disobey the commander's vehicle, they will be fined. In serious cases, the site will be cleaned up.

2. The assembled vehicles shall not be disorderly, and obey the distribution command. If there are vehicles strung to other construction sites, one month's freight will be deducted and the site will be cleared.

3. If the vehicle is evacuated without reason, so that the contract cannot be continued or economic losses are caused, the breaching party shall be responsible for compensating the economic losses, and the compensation standard shall be 50% of the monthly salary.

4. The refueling of each equipment shall be carried out according to the indicators specified by Party A, and the oil price shall be subject to the market price. If the oil price rises, Party A will subsidize it.

5. In case of work stoppage caused by force majeure and government actions, the term of this contract shall be terminated or postponed by mutual consent.

6. Matters not covered in this contract can be supplemented by the terms of the agreement, which have the same legal effect. This contract is made in duplicate, one for each party, and shall come into effect as of the date of signature.

Party A:

Party B:

Date of signing:

Earthwork contract. Contract 4 Abbreviated Name of Party A:

Name of Party B:

Based on the principle of equality and mutual benefit, according to the Labor Law, Economic Contract Law and other relevant national laws and regulations. Through negotiation, Party A and Party B have reached the following contract agreement on the earthwork leveling project of the municipal square (central square):

1. Project contracting contents: all work contents such as earthwork excavation, transportation, backfilling, spoil, site leveling, dredging and surface cleaning (earthwork excavation is 241758m3, backfilling and rolling is 52,767m3, spoil 18899 1 m3, and site leveling is 70%.

2. Project location: opposite to Yibin Municipal Government.

Three. Safety: During the construction period, Party B shall be responsible for all safety accidents.

Four. Engineering technical requirements: Party B shall carry out the construction according to the design drawings, current construction specifications and technical requirements of the project department (Party A), make safety construction disclosure and organize the construction. Party B shall be responsible for road maintenance and sanitation during earthwork transportation.

5. Party B shall carry out the construction in strict accordance with the requirements of standards, specifications and design drawings and the instructions issued by the project department according to the contract, and accept the inspection and inspection of the project department at any time. Once the project quality fails to meet the agreed standards, the project department will require Party B to re-construct. If it fails to meet the agreed standards due to Party B's reasons, Party B shall bear the cost of re-construction and the construction period will not be postponed.

6. Calculation of engineering quantity: Calculate the excavation engineering quantity according to the construction drawings (the comprehensive unit price of excavation has included all contents such as earthwork excavation, transportation, backfilling, soil abandonment, site leveling, dredging and surface cleaning). In the process of construction, when the engineering quantity increases or decreases and new projects are added, the contract price will be adjusted and a supplementary agreement will be signed after confirmation by the project department. The spoil is outside the south side of the construction site, and the spoil is in the red fan spoil ground. The height of earthwork accumulation is lower than that specified in the planning and design.

Seven. Price: This project adopts the comprehensive unit price lump sum based on the excavation quantity (the comprehensive unit price of excavation has included all contents such as earthwork excavation, transportation, backfilling and rolling, soil abandonment, site leveling, dredging and surface cleaning). The comprehensive unit price is RMB 6. 10 yuan/m, and Party B is solely responsible for the construction.

Eight, obstacles in the construction site (including house demolition, water and electricity demolition) shall be removed by Party A, which will never affect Party B's construction. Party A shall be responsible for solving the factors that affect the normal construction of Party B in the spoil ground outside the red line of the construction site. ..

9. Civilized construction: in line with the requirements and standards of civilized construction of city appearance. In case of violation of relevant regulations, Party B shall be responsible for the consequences.

10. Time limit: complete all contracted projects within 40 working days (Party A will fine the contractor 2000 yuan for every day of delay due to Party B's reasons). In case of irresistible natural factors or special reasons, the construction period can be extended, but it needs the signature of Party A. If the shutdown is caused by Party A's reasons, the shutdown loss shall be calculated according to relevant regulations, and Party A shall be responsible for it.

1 1. Payment method: Party B will enter the site immediately after receiving Party A's notice of entry. Party A pays 6,543,800 yuan in advance for the first time (within three days after entering the site), and pays 50% according to the project progress every 654.38+ 00 days. After the project is completed and accepted, both parties shall complete the project settlement, and Party A shall pay 75% of the project payment within 7 days after both parties complete the project settlement. Party A shall pay off the balance of Party B within 3 months.

12. Settlement method: Party B shall settle with Party A in the form of mechanical fuel fee and wages of shift workers.

13. Deposit: When both parties sign the contract, Party B pays a deposit of 5,000 yuan to Party A, which will be refunded (interest-free) after the project is accepted.

Fourteen Liability for breach of contract: In case of unilateral breach of contract during the execution of the contract, the breaching party shall bear all losses of the observant party, and the breaching party shall pay the observant party a penalty of RMB 5,000. In case of dispute, the national labor law and economic contract law shall apply.

15. This contract shall come into effect after being signed by both parties, and shall automatically become invalid after the project payment is completed. This agreement is made in quadruplicate, with each party holding two copies. Matters not covered in this contract shall be settled by both parties through friendly negotiation.

Party A:

Party B:

Date of signing:

Simple earthwork contract 5 Party A:

Party B:

According to the Contract Law of People's Republic of China (PRC) and related laws, and in combination with the actual situation on site, Party B's motorcade undertakes labor contract for part of Party A's earthwork in the name of Party A's construction site. In order to clarify the rights, obligations and responsibilities of both parties, both parties * * reach the following agreement:

Project overview:

I. Project Name: Sandu and Beiping Coal Mines in Xiyang County

Two. Project content: earthwork excavation and transportation

3. Project volume: about 20xx days to about 20xx days, tentatively for one year, and the cooperation is completed.

1. Party B's construction vehicle has two front wheels and eight rear wheels, and the power is greater than 3 10 horsepower.

2. Drivers must have more than two years' driving experience and be in good health, giving priority to the construction safety of vehicles on site. In case of traffic accident, disability accident or vehicle damage during the construction, it has nothing to do with Party A, and Party A will assist in the coordination and handling, and the expenses shall be borne by Party B. ..

3. Party A is responsible for coordinating the relationship between the owner and the villagers, maintaining the smooth construction of vehicles and creating a good construction environment and comfortable roads.

4. During the construction period, drivers are forbidden to drink alcohol, and pay special attention to fighting and theft. Violators will bear the consequences, and Party A has the right to impose a fine of 500-200 yuan, and bear legal responsibilities and civil compensation until they appear.

5. Party A is responsible for arranging accommodation and parking spaces for Party B's personnel and vehicles, and the expenses incurred shall be borne by Party B..

6. Party A shall guarantee that Party B's vehicle will work for more than 25 working days every month, except for irresistible man-made work stoppage, such as rain, snow, superior inspection and moving away from the site. If Party A fails to release the working day, Party A will compensate the driver and living expenses of each car, and Party A will issue a certificate to Party B in 300 yuan every day and settle the account.

7. In order to ensure the completion of the project tasks and prevent vehicles from escaping, Party A will deduct 5% of the day's deposit at the time of settlement, but both parties are healthy. The detention period is 30 days and will be returned to the owner after the project is completed. In case of any objection during construction, the representatives of Party A and Party B shall settle it through negotiation until there is no dispute between the two parties. If individual vehicles run around for no reason, they will be fined 5000- 10000 yuan in addition to the 5% deposit.

8. Party A is responsible for Party B's vehicle to achieve 50% profit. When the average number of trips is less than 20 days, Party B has the right to stop work and leave, or make a decision through consultation, but cheating is not allowed. Obey the scheduling and management of site management personnel and make unified deployment. It is forbidden to be choosy in construction, which will cause traffic jams, confusion and slack, affect the construction progress, and give certain economic penalties.

Fourth, the way to calculate the unit price and fine

1. The vehicle capacity and the current measurement between the owner and Party A are the settlement basis, and the length × width × height of each vehicle is the standard. If it is necessary to increase the engineering quantity, both parties shall report in advance for measurement as the settlement basis.

2. The settlement method is one day, and the oil money will be paid off after deduction. At the time of settlement, Party B chooses one person as the representative, and the bill is collected for settlement, while others have no right to settle. Note (except for bank power failure, it will not be delayed for more than two days.

3. The vehicle transfer fee is RMB per vehicle, which will be deducted when the freight is settled within ten days.

4. If there are any matters not covered in this contract, both parties shall settle them through negotiation. If negotiation fails, both parties may bring a lawsuit to the people's court where the construction is located.

5. This contract is made in triplicate, each party holds one copy, and the notary office holds one copy, which shall come into effect after being signed by both parties.

Party A:

Party B:

Date of signing:

Simplified Earthwork Contract 6 Party A: _ _ _ _ _ (hereinafter referred to as Party A)

Party B: _ _ _ _ _ _ (hereinafter referred to as Party B)

According to the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and other relevant regulations, in line with the principle of equality, mutual benefit and common development, in order to clarify the relationship of responsibilities, rights and interests of both parties, and in combination with the specific conditions of this project, Party A and Party B have reached the following agreement through full consultation for common compliance.

I. Overview of earthwork excavation and transportation engineering and contract scope

Project name: _ _ _ _ _ _ _

Project location: _ _ _ _ _ _ _

Scope of earthwork excavation and transportation: _ _ _ _ _ _ _

Second, the scope of contracting for earthwork excavation and transportation

1, according to the design documents, after the construction technicians pay off, The quantities of excavation and transportation shall be _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

2, according to the survey technicians pay-off leveling one-time dig in place, flat, slope meets the requirements, the depth conforms to the specification acceptance.

Third, the construction cycle

The total construction period is _ _ _ _ _ _ _ _ _ _ _ years from the date when Party A notifies Party B to start construction to the completion of all earthwork excavation and transportation.

Four, the way of contracting and the price of labor transfer fee

65438+

2, according to the design pay-off acceptance quantity calculation, yuan per cubic meter.

Verb (abbreviation of verb) payment method

After the completion and acceptance of the foundation earthwork of each building, 80% of the foundation earthwork of the building will be paid, and the rest will be paid in one lump sum after the completion and settlement.

Rights and obligations of both sides of intransitive verbs

1, Party A's engineers and technicians are responsible for the measurement of excavation scope, technical guidance, setting-out depth and leveling management and coordination in excavation and transportation engineering.

2. Party B is responsible for organizing construction machinery to enter the site, dig and transport, manage personnel, and coordinate the relationship between municipal supervision and inspection. The machinery and personnel entering the site must obey the management of the site construction personnel, and at the same time abide by the municipal health management and construction civilization norms.

3. Party B is responsible for the safety, living, fuel and other expenses of machinery and mechanical personnel, and shall be responsible for those who violate the management of city supervisors.

Seven. responsibility for breach of contract

The liquidated damages of this contract are 20% of the total project amount, which shall be paid by the breaching party to the observant party.

Eight. others

Party A:

Party B:

Date of signing: