Harbin Metro Line 1 start time completion time full length

The first phase project and southern extension project of Metro Line 1 under construction starts from Hanan Station in the west, along Xuefu Road and Dazhi Street, and ends at Hadong Station in the east, with a total length of 17.48 kilometers. The main construction scale It includes 18 stations, 1 depot, 1 parking lot, 1 control center, 2 ground main substations, electromechanical equipment systems and other supporting facilities. The estimated investment is 10.35 billion yuan, with a total construction period of 4 years. The project started on September 29, 2008. It is planned to complete the civil engineering in April 2011, complete the track laying of the entire line in March 2012, complete the equipment installation and catenary erection of the entire line in June 2012, and be completed and open to traffic by the end of December 2012.