Emergency plan for rain and snow during the Spring Festival
When there is sudden snowfall, it is necessary to ensure traffic safety and environmental improvement on the Third Ring Road, and to formulate emergency plans. Here is what I bring to you, hoping to give everyone some information. Harvest! ? ?
This emergency plan is applicable to the emergency response to all projects under construction in the winter rain and snow weather project department during the Spring Festival when large-scale rain or snow occurs.
1 Compilation basis and policy principles
Occupational safety and health management system audit standards
Emergency preparedness and response control procedures
Adhere to the policy of "safety first, prevention first", "protecting personnel safety first, protecting the environment first", and implement the principles of "remitting readiness, unified command, efficient coordination and continuous improvement".
2 Hazard source analysis
The sudden emergencies that may occur on site are:
1. Traffic accidents in rain, snow and freezing weather
2. Rain and snow temporary construction protection
3 Emergency preparation
The project department established an emergency rescue team for rain and snow during the Spring Festival:
Team leader: Chen Guisheng 18762962595 < /p>
Deputy team leader: Li Shaofeng 15851972233, Li Fuhai 18762204999
Members: Shi Rongmin, Li Jinxi, Li Shuai, Li Fuying, Feng Xianmei
Responsibilities: Emergency rescue team: in the event of an accident When necessary, organize a temporary rescue, report the situation to superiors in a timely manner, and request support from relevant superior departments.
Team leader: Responsible for the command of emergency rescue for this project.
Deputy team leader: Assist the team leader in the command of emergency rescue.
Material installation: Team leader Chen Guisheng is responsible for mechanical support and material deployment.
Information contact: Deputy team leader Li Shaofeng is responsible for ensuring smooth flow of information.
Emergency rescue team: headed by deputy team leader Li Fuhai and composed of people left behind during the Spring Festival.
Material preparation serial number name quantity unit 1 5 shovels 2 10 brooms 3 1 loader
4 Emergency response
When an accident occurs, the scene is found Personnel should take measures to control the spread or expansion of the situation and notify the emergency rescue team headquarters. After receiving the notification report, the project department immediately activated the emergency preparedness plan, organized relevant personnel, devices, materials, facilities and equipment to rush to the scene to take effective measures.
5 Emergency measures and operating procedures
Clear snow and ice on the roads and keep them clean. Active emergency plans should be adopted for the following emergencies:
5.1 Emergency Plan for Preventing Mechanical Injury in Rainy and Snowy Weather in Winter
1 Strengthen pre-holiday inspection and maintenance of mechanical devices, and promptly Eliminate accident risks.
2 After the snowy day, check the mechanical devices in time, clean up the snow and ice on the machinery in time, and follow the shutdown and power-off warning sign system.
5.2 Emergency plan for preventing electric shock injuries in winter rain and snow
1 Listen to the weather forecast in time and protect the switch box at the accident site against rain and snow in advance. Devices not in use must be turned off before rain or snow.
2 After rain or snow, clean up snow and ice in time, and check whether the power supply and wires are damaged or leaking electricity. If any electrical equipment is found to be damaged, repair it in time to avoid electric shock injuries.
5.3 Traffic Accident Emergency Plan
1. If snow and ice are found on the road after snow, immediately organize personnel to clean the road and clean important intersections. While ensuring smooth construction roads, ensure the safety of social traffic.
2 According to the on-site conditions, traffic diversion personnel should be arranged at major intersections to direct traffic and prevent traffic accidents.
3. After the snow, the operator who installed the mobile phone must make a targeted and individual explanation to prevent traffic accidents.
5.4 Temporary construction protection emergency plan
1 Listen to the weather forecast in time, and put away unnecessary devices before snowfall to prevent snow accumulation.
2 Clean the snow on temporary facilities promptly after snow to prevent collapse accidents.
3 When clearing snow, construction workers must take safety precautions to avoid personal injury.
4 If temporary construction facilities are damaged, construction workers are not allowed to enter the building, and snow and damaged buildings must be cleared in time.
6 Emergency Plan Safeguard Measures
1. Strengthen duty and information communication. During the Spring Festival rain, snow, strong winds, and cooling weather, a 24-hour duty system should be implemented, communication channels should be opened, and relevant situations should be understood and grasped at any time, and reports should be reported at any time.
2. Material support. The logistics support team should be responsible for the reserve of emergency supplies, ensuring that they are thoughtful, timely and provide effective support.
3. Technical support. Understand the weather conditions promptly and accurately, and make timely technical preparations for preventing rain and snow.
4. Publicity and education.
Strengthen publicity and education for left-behind personnel to enhance safety knowledge and self-protection awareness.
Changshu City Third Ring Road Renovation S9 Standard Project Management Department of the Third Company of China Communications Construction Company No. 3 Company
January 5, 2012